Step 1. Application for Preliminary Zoning Review Submit Date:
3/22/2019
Step 2. Preliminary Zoning Review Meeting:
5/1/2019
Step 3. Applicant Work Time Period:
5/1/2019 to 10/28/2019
The public participation meeting was held on 11/20/2019 at 6:00 p.m. at 2705 Hurt Bridge Road, Cumming, GA 30028.
Step 4. Application for Board Consideration Submit Date:
11/22/2019
Step 5. Planning Commission (PC) Public Hearing:
5/19/2020
Step 6. Board of Commissioners (BOC) Meeting:
6/18/2020